Disco alerts Plateau, Bauchi, Gombe of 6-day power outage

The management of Jos Electricity Distribution Company has said its customers in Plateau, Bauchi and Gombe states will experience power outage for six days to enable the company carry out major maintenance. Head of Corporate Communications of Jos Disco, Dr Friday Adakole Elijah, said the outage will commence from August 28 to September 2. Cross […]

Disco alerts Plateau, Bauchi, Gombe of 6-day power outage

Jos Electricity Distribution

The management of Jos Electricity Distribution Company has said its customers in Plateau, Bauchi and Gombe states will experience power outage for six days to enable the company carry out major maintenance.

Head of Corporate Communications of Jos Disco, Dr Friday Adakole Elijah, said the outage will commence from August 28 to September 2.

Cross River APC demands return of nat’l women leader position

NASFAT president tasks new ministers on performance

He said the planned outage by TCN is “to enable its EPCC contractors safely connect gantry beam of the new APO line to the existing Lafia line-Jos 330kv double circuit.”