TCN restores power 15 days after fire incident
The Transmission Company of Nigeria (TCN) has restored power supply to Birnin Kebbi and its environs 15 days after fire gutted its substation. There was wild jubilation in Birnin Kebbi metropolis when light was restored around 9.15pm. Children and adults took to streets to jubilate over the return of power in their various residential areas. […]
The Transmission Company of Nigeria (TCN) has restored power supply to Birnin Kebbi and its environs 15 days after fire gutted its substation.
There was wild jubilation in Birnin Kebbi metropolis when light was restored around 9.15pm. Children and adults took to streets to jubilate over the return of power in their various residential areas.
It would be recalled that the TCN power house and two transformers were destroyed by the fire, which in turn affected Kebbi and Sokoto states.
2023 Presidential Election: No Apology For Backing A Northern Candidate – Abdullahi Adamu
GAIN empowers 1,760 rural farmers
The management of the TCN had initially planned to restore power to Kebbi from Sokoto having restored Sokoto light from Talata Mafara substation but it later decided to feed Kebbi from the transformer through which Niger Republic was being fed.